Neoen shut down Australian solar-plus-storage plant after 7 years

Neoen shut down Australian solar-plus-storage plant after 7 years

The DeGrussa solar and battery center in remote Western Australia– the biggest incorporated off-grid solar and battery storage center in Australia when it was released– has actually reached end of life, states property owner Neoen.

From pv publication Australia

French renewable resource giant Neoen has actually verified the DeGrussa solar and battery center in the heart of Western Australia’s goldfields area will be taken apart after 7 years of operations.

The DeGrussa center, consisting of 10.6 MW of PV and a 6 MW lithium-ion battery energy storage system teamed with a diesel-fired generator, was commissioned at West Australian mining business Sandfire Resources’ Degussa copper mine website, 900 kilometers northeast of Perth, in June 2016.

The solar hybrid power system has actually because provided almost 20% of the mining operation’s yearly power requirements and cut its emissions by about 12,000 tonnes of co2 a year.

Sandfire bought the power under a preliminary 5.5-year arrangement however that was extended as the mining operation pressed beyond its initial 2021 closure date. The mine has actually nevertheless now stopped operations, signalling completion of life for the DeGrussa solar and battery center.

In a declaration shown pv publicationNeoen stated it prepares to eliminate the photovoltaic panels, along with the rest of its center and to fix up the website.

Environment Energy Finance Director Tim Buckley stated the taking apart came as not a surprise with completion of mine life “definitely popular” when they solar hybrid power system was commissioned

“There is not a surprise there,” he stated, including that in spite of its brief life expectancy, the DeGrussa power task has actually been a “dazzling success.”

Buckley stated the task, which brought in AUD 20.9 million ($13.7 million) in financing from the Australian Renewable Energy Agency (ARENA) and AUD 15 million in financial obligation financing from Clean Energy Finance Corp. (CEFC), became part of the “action modification that took solar from being a prospective innovation to being now essential to the change and decarbonization of the Australian electrical power system.”

“Given Australia has actually gone on to end up being a world leader in both the solar and battery energy storage systems suggests this was a dazzling success, over-delivering in regards to the financials and task’s prepared life and the knowing by doing of this pilot-scale, world-leading implementation,” he stated. “The capability, the scale, the innovation enhancements, the software application combination, all the knowings that have actually gone on, Degrussa was a core part of the early knowing by doing.”

Popular material

Buckley stated the job had actually offered essential knowings in how off-grid energy requirements are going to be consulted with Australia now is welcoming the energy shift.

“Our most significant business are BHP and Riosubstantial balance sheets, big capacity and substantial energy requirements and they are beginning to accept the knowing by doing that ARENA has actually been promoting for the previous years and Degrussa was a timeless example,” he stated.

Even as it is being taken apart, the DeGrussa task might supply lessons with Neoen checking out chances to repurpose the 34,080 photovoltaic panels and other facilities that is set up throughout the 20-hectare website.

“Our choice is for the photovoltaic panels to be re-used as they stay in great condition,” the business stated, including that it “is presently examining chances to discover a 2nd life for the photovoltaic panels and for the other primary parts such as the inverters, transformers and the battery pack.”

The DeGrussa turning point comes as Western Australian government-owned energy Synergy revealed that it has actually begun the decommissioning of the Ten Mile Lagoon and Nine Mile Beach wind farms near Esperance in the state’s southwest.

9 Mile and Ten Mile wind farms were set up more than 20 years earlier and have actually reached their end of life.

Throughout decommissioning, 2 of the wind turbines are being contributed to North Metropolitan TAFE for renewable resource training functions and 6 wind turbines will be repurposed at brand-new wind farm websites in the Perth area.

The task is anticipated to be finished by the end of 2024.

async” src=”https://www.pv-magazine-australia.com/wp-content/uploads/sites/9/2024/01/Solar-aerial-degrussa-600×420.jpg” alt width=”600″ height=”420″ data-attachment-id=”88063″ data-permalink=”https://www.pv-magazine-australia.com/2024/01/18/degrussa-solar-and-battery-hub-labelled-brilliant-success-as-decommissioning-begins/solar-aerial-degrussa/” data-orig-file=”https://www.pv-magazine-australia.com/wp-content/uploads/sites/9/2024/01/Solar-aerial-degrussa.jpg” data-orig-size=”2560,1794″ data-comments-opened=”1″ data-image-meta=”” data-image-title=”Solar-aerial degrussa” data-image-description data-image-caption=”

Neoen is hoping to find a new home for the 34,080 solar panels installed at DeGrussa.

” data-medium-file=”https://www.pv-magazine-australia.com/wp-content/uploads/sites/9/2024/01/Solar-aerial-degrussa-600×420.jpg” data-large-file=”https://www.pv-magazine-australia.com/wp-content/uploads/sites/9/2024/01/Solar-aerial-degrussa-1200×841.jpg”> < img decoding="async" src="https://www.pv-magazine-australia.com/wp-content/uploads/sites/9/2024/01/Solar-aerial-degrussa-600x420.jpg" alt width="600" height="420" data-attachment-id="88063" data-permalink="https://www.pv-magazine-australia.com/2024/01/18/degrussa-solar-and-battery-hub-labelled-brilliant-success-as-decommissioning-begins/solar-aerial-degrussa/" data-orig-file="https://www.pv-magazine-australia.com/wp-content/uploads/sites/9/2024/01/Solar-aerial-degrussa.jpg" data-orig-size="2560,1794" data-comments-opened="1" data-image-meta =" " data-image-title="Solar-aerial degrussa" data-image-description data-image-caption ="

Neoen is intending to discover a brand-new home for the 34,080 photovoltaic panels set up at DeGrussa.

data-medium-file=”https://www.pv-magazine-australia.com/wp-content/uploads/sites/9/2024/01/Solar-aerial-degrussa-600×420.jpg” data-large-file=”https://www.pv-magazine-australia.com/wp-content/uploads/sites/9/2024/01/Solar-aerial-degrussa-1200×841.jpg” >

Image: Sandfire Resources

This material is safeguarded by copyright and might not be recycled. If you wish to work together with us and want to recycle a few of our material, please contact: editors@pv-magazine.com